It was pouring down and I didn't expect anything. Went by, poor carpenters, no wonder they get paid so much!
The trials and tribulations of building my first house(s) ... and second.
Friday, May 31, 2019
Saturday, May 25, 2019
Slab stage completed!
Things are moving faster than I expected. So fast that I didn't have time to get a pre slab inspection!
14 May
Retaining walls completed - much higher than I expected. Not quite sure how I'm going to do the access for next door.
21 May
Some piles of stuff
23 May
Pre slab prepartation
24 May
Concrete poured!
Bit worried though as it's been raining A LOT
Saturday, May 4, 2019
Excavator
According to next door, there's some action!
Still some delay with building permit - surveyor wants my retaining wall to be engineered.