Friday, May 31, 2019

Frames

It was pouring down and I didn't expect anything.  Went by, poor carpenters, no wonder they get paid so much!

Saturday, May 25, 2019

Slab stage completed!

Things are moving faster than I expected.  So fast that I didn't have time to get a pre slab inspection!

14 May 
Retaining walls completed - much higher than I expected.  Not quite sure how I'm going to do the access for next door.



21 May
Some piles of stuff


23 May
Pre slab prepartation

24 May
Concrete poured!

Finished slab!





Bit worried though as it's been raining A LOT

Saturday, May 4, 2019

Excavator

According to next door, there's some action!



Still some delay with building permit - surveyor wants my retaining wall to be engineered.